Tentative Work Schedule

November 9, 2020

 

Work in the NE section consists of Mowing Starke Country Club wit Zero Turns

 

Work in the NW section consists of Grading NW 201st St., Mowing ROW on NW 36th, Clean up tree debris on NW CR 125 and Mow NW CR 229A and NW CR 233

 

Work in the SE section consists of Grading SE 49th ands SE 46th and Picking up, Loading and Chipping debris on SE CR 21B and SE 31st St.

 

Work in the SW section consists of Grading SW 85th Lane

 

 

We received 2 DOC Squads for a total of 9 people

 

1 Squad will be Weed eating the Guardrails on SW CR 18 before Brooker and then going to assist with Chipping on SE CR 21B

 

1 Squad will be assisting with Chipping on SE CR 21B