Tentative Work Schedule

Work in the NW section consists of Finishing crossover pipe and building up NW 193rd St., Clean out ditch on NW 53rd Ave., Cut, Trim & Chip trees and debris and Mow with Side Arm Mower on NW 23rd St. and Patch pot holes at the intersection of NW 177th St. and NW CR 229

 

Work in the SE section consists of Milling SE 66th St. and Patching a pot hole at the intersection of SE CR 18 & SR 100

 

Work in the SW section consists of Patching a washout where Butler Road and SW 155th St. meet

 

 

We received 3 DOC Squads for a total of 20 people

 

1 Squad will be patching pot holes at the intersection of SE CR 18 & SR 100 and at the intersection of NW 177th St. and NW CR 229 and a washout where Butler Rod and SW 155th St. meet

 

1 Squad will be Cutting, Trimming and Chipping trees on NW 223rd St.

 

1 Squad will be Picking up trash and Weed Eating SE CR 18 from Hampton to SR 100