Tentative Work Schedule

October 15, 2019

 

Work in the NE section consists of Grading NE 12th, NE 19th Ln. & NE 21st Ln and Digging the ditch on NE 19th Ave.

 

Work in the NW section consists of Grading NW 178th Loop and all roads off 301, Mowing an Outfall Ditch from NW 223rd St. to NW CR 225 and NW CR 225

 

Work in the SW section consists of Grading SW 155th, SW 136th, SW 160th & SW 111th St., Picking up limbs and debris and Patching troughs on SW CR 235, Mowing Crosby Lake Area and Building a pad at the Sampson City Fire Department on SW CR 227

 

 

We received 3 DOC Squads for a total of 16 people

 

1 Squad will be Picking up trash and Weed eating all of SE 21st Ave.

 

1 Squad will be Cleaning out ditch pavings on SE CR 235

 

1 Squad will be directing traffic and Digging the Ditch on NE 19th Ave.

.