Tentative Work Schedule

February 25, 2019

 

Work in the NE section consists of Cleaning out a  Ditch on NE 161st and Install culvert at NE 154th St.

 

Work in the NW section consists of Grading NW 71st, 193rd & NW 75th, Dig ditch on NW CR 235 (Nettle's ditch) and Install culvert at 20289 NW 57th Pl.

 

Work in the SE section consists of Grading SE 49th, 86th and towards 100

 

Work in the SW section consists of Grading SW 163rd and Patching shoulders on SW CR 231

 

 

We received 3 DOC Squads for a total of 14 people

 

1 Squad will be assisting with Cleaning out a Ditch on NE 161st

 

1 Squad will be Picking up trash and Weed Eating on SW CR 18

 

1 Squad will be Laying Sod over Crossover pipes on NW 216th St. and Picking up trash and Weed Eating on NW 216th St.