Tentative Work Schedule

April 9, 2019

 

Work in the NW section consists of Zipping NW 219th St. and Digging a ditch on NW 53rd Ave.

 

Work in the SE section consists of Patching Pot holes on SE 17th Ave

 

Work in the SW section consists of Grading SW 101st Ave., Digging the ditch on SW CR 100A (Edwards Road) and Filling in a driveway in Brooker

 

 

We received 3 DOC Squads for a total of 15 people

 

1 Squad will be Patching Pot Holes on SE 17th Ave. then a driveway in Brooker

 

1 Squad will be Digging and Cleaning out a ditch on SE 23rd Ave. off SE CR 18

 

1 Squad will be Digging the itch on SW CR 100A (Edwards Road)