Tentative Work Schedule

August 27, 2020

 

Work in the NW section consists of Grade NW 66th Ave., Cut Shoulders and Mow NW CR 225, Cut ROW on NW 216th St. & NW 233rd and Patch Pot Holes on NW 62nd Ave. and NW 177th St.

 

Work in the SW section consists of Cleaning out Concrete Ditches on SW CR 231 & SW CR 18 and Mowing SW 75th Ave. and  SW CR 100A

 

 

We received 2 DOC Squads for a total of 9 people

 

1 Squad will be assisting with Patching Pot Holes on NW 62nd Ave. and NW 177th St.

 

1 Squad will be Weed eating Ditches on NW 219th St.

 

County Officer and two (2) Temporary Laborers will be directing traffic on NW CR 225 for Cutting Shoulders