Work Schedule

 

Work in the NE section consists of Grading

 

Work in the NW section consists of Grading, Pulling Ditches, Ditch work and Patching driveways

 

Work in the SE section consists of Mowing and Cutting, Trimming & Chipping

 

Work in the SW section consists of Zipping a road and Patching driveways

 

 

We received 1 DOC Squads for a total of 7 people

 

1 Squad will be assisting in Cutting, Trimming & Chipping in the SE section

 

1 Squad will be assisting with directing traffic in the NW section

 

 

1 Squad from The Transition House (3 people) will be assisting with patching driveways in the SE section