Tentative Work Schedule

February 14, 2019

 

Work in the NE section consists of Chipping NE 20th Lane and Mowing NW 1st Ave.

 

Work in the NW section consists of Grading NW 209th St., NW 41st Ave. & NW 35th Ave., Grading NW 38th Ave. & NW 36th Ave. with the Road Boss, Dig the ditch on NW CR 235  (Nettle's ditch) and Patch pot holes on NW 214th 

 

Work in the SE section consists of Adding milling and limerock to SE 46th Loop

 

Work in the SW section consists of Grading SW 180th Ave.

 

 

We received 2 DOC Squads for a total of 11 people

 

1 Squad will be Patching pot holes on NW 214th

 

1 Squad will be Chipping limbs and debris on NE 20th Lane