Tentative Work Schedule

April 20, 2021

 

Work in the NE section consists of Prepping NE 204th St. for Fog Sealing

 

Work in the NW section consists of Grading NW 41st Ave., Cleaning out the ditch on NW 71st Ave. and Patching Pot Holes on NW 219th St.

 

Work in the SW section consists of Adding Limerock and Grading SW 160th Ave., Mowing Sampson Lake Boat Ramp and Mowing SW CR 231 (Dedan Loop) and SW CR 18

 

 

We did not receive any DOC Squads nor any Inmates