Tentative Work Schedule

November 3, 2020

 

Work in the NE section consists of Cutting ROW on NE 213th

 

Work in the NW section consists of chipping, Mulch and Keeping limbs off the road on NW CR 125 and Prepping NW CR 214

 

Work in the SE section consists of Grading SE 50th (both ends), SE 51st and SE 46th Loop, Cut and trim on SE CR 214 and Mowing SE CR 100A and SE 44th Ave.

 

Work in the SW section consists of Grading SW 92nd St., SW 105th and SW 101st Ave.

 

 

We received 1 DOC Squad with 5 people and they will be assisting with Chipping on NW CR 125