Tentative Work Schedule

January 11, 2024

 

Work in the NE section consists of Patching Pot Holes and Driveways on NE CR 200B

 

Work in the NW section consists of Grading NW 41st Ave., NW 219th St., NW 53rd Ave. and NW 44th Ave., Patching Pot Holes and Driveways in Pleasant Grove area and Hauling Dirt to New River Landfill

 

Work in the SE section consists of Grading SE 72nd St., SE 71st St. and SE 73rd St

 

Work in the SW section consists of Grading SW 136th St. and SW 137th St. and Mowing Shoulders of the Road on SW 160th Ave.

 

 

We received 2 DOC (BCSO-JAIL) Officers and 3 Inmates 

 

1 Officer will be assisting in Maintenance

 

1 Officer and 3 Inmates will be Picking up Trash on SW CR 18 and SW CR 231