Tentative Work Schedule

October 19, 2020

 

Work in the NE section consists of Grading Carter Road. NE 227tth, NE 6th Ave & NE 7th Ave

 

Work in the NW section consists of Trimming trees, Chipping & Mulching NW CR 235, Mowing ROW on NW 44th Ave., Fixing a driveway on NW 53rd and Fix a culvert on on NW 193rd St.

 

Work in the SE section consists of Mowing SE CR 18

 

Work in the SW section consists Grading SW 168th, SW 137th & SW 144th, Spraying SW 106th Ave with Fog Seal, Chipping SW CR 231 and Mowing SW CR 225 & SW CR 18 

 

 

We received 2 DOC Squads for a total of 8 people

 

1 Squad will be assisting with Chipping on NW CR 235

 

1 Squad will be Weed eating a ditch at the end of NE 15th Ave.