Work Schedule

 

Work in the NE section consists of Grading, Grading milled roads & Cutting, Trimming and Chipping

 

Work in the NW section consists of Grading milled roads, Cutting, Trimming and Chipping and Patching pot holes and Patch a Bridge in the NW section

 

Work in the SE section consists of Milling part of a road and Grading

 

Work in the SW section consists of Grade, Mow, Digging ditches, Installing culverts, Patching a hole at Hampton Boat Ramp and Edge sidewalks & Trim trees in Brooker

 

 

We received 3 DOC Squads for a total of 16 people

 

1 Squad will assist in Cutting, Trimming and Chipping in the NW and NE section

 

1 Squad will assist in patching a hole at Hampton Boat Ramp, Edge sidewalks and Trim trees in Brooker and Patch bridge on NW CR 200A

 

1 Squad will be Picking up trash, weed eating and mowing ahead of the Mower in SW section

 

 

1 Squad from The Transition House (3 people) will be Patching pot holes in the NW section