Tentative Work Schedule

October 24, 2019

 

Work in the NE section consists of Cleaning out ditch on NE 171st St. and Mowing NE 20th Ave., NE 200B and NE 17th Loop

 

Work in the NW section consists of Grading NW 74th Ave., NW 84th Ave., NW 35th Ave., NW 209th, NW 41st and NW 49th, Dig the Outfall ditch and Pack on NW 219th Ter. and Patch Pot Holes at the intersection of NW CR 225 & NW 60th Ln.

 

Work in the SW section consists of Mowing SW CR 18, SW CR 231 & SW CR 225

 

 

We received 2 DOC Squads for a total of 7 people

 

1 Squad will be Picking up trash and Weed eating on NW 55th Ave.

 

1 Squad will be directing traffic, Cleaning out & Weed eating a ditch on NE 171st St.