Tentative Work Schedule

October 14, 2019

 

Work in the NE section consists of Grading NE 171st, NE 5th, NE 173rd, NE 19th & NE 21st

 

Work in the NW section consists of Grading NW 198th and Mowing NW 76th Ave., NW 37th & NW CR 225, NW 185th, NW 84th, NW 188th, NW 193rd & NW 75th

 

Work in the SE section consists of Cleaning out the ditch on SE 21st Ave.

 

Work in the SW section consists of Grading SW 155th, SW 136th & SW 160th, Patching Pot Holes and Trough at 12703 SW 69th Ln. and Picking up trees and debris at SW 69th (Hampton Lake Boat Ramp

 

 

We received 3 DOC Squads for a total of 15 people

 

1 Squad will be Assisting with Picking up trees and debris on SW 69th (Hampton Lake Boat Ramp)

 

1 Squad will be Cleaning out ditch pavings on SW CR 235

 

1 Squad will be Assisting with traffic control and cleaning out ditches on SE 21st Ave.