Tentative Work Schedule

April 6, 2021

 

Work in the NW section consists of Grading NW 41st Ave., Ditch work on NW 178th Loop and NW 214th St. and Mowing NW 59th Ave. and NW CR 225

 

Work in the SE section consists of Cleaning the Fence Line at the Old Land Fill and Patching Pot Holes on SE 15th Ave.

 

Work in the SW section consists of Grading SW 132nd Ave.

 

 

We received 2 DOC Squads for a total of 10 people

 

1 Squad will be assisting with Cleaning up the Fence Line at the Old Land Fill

 

1 Squad will be Picking up trash and weed eating on NW CR 225