Tentative Work Schedule

December 17, 2019

 

Work in the NE section consists of Grading NE 173rd, NE 19th Ln. and NE 21st Ln.

 

Work in the NW section consists of Grading NW 219th St.

 

Work in the SE section consists of Grading roads off of SE CR 18, Starting at SE SR 100 and going towards Hampton

 

Work in the SW section consists of Shoulder work on SW CR 235, Mowing SW 101st Ave and SW CR 225 and Removing and replacing two (2) 24"X30' Crossover pipes and Installing one (1) 30"X30' Crossover pipe to restore to the original size pipe Pre-Irma storm.

 

 

We received 2 DOC Squads for a total of 9 people