Work in the NE section consists of Digging Ditches at NE 7th and NE CR 125

 

Work in the NW section consists of Grading NW 75th, NW 71st and NW 193rd and Mowing around Guardrails on NW CR 225A

 

Work in the SE section consists of Grading SE 125th St., SE 59th Ave, and Roads off of SE CR 18 going from 301 towards SE SR 100

 

Work in the SW section consists of Grading SW 82nd Ave., Cutting, Trimming and Hauling off Trees and Limb debris  on SW CR 237 and SW CR 18 and Mowing SW CR 18 and SW CR 225

 

 

We received 2 DOC (BCRD-JAIL) Officers and a total of 4 Inmates

 

1 Squad and 1 Inmate will be assisting with Cutting, Trimming and Loading Trees, Limbs and Debris for Hauling off from SW CR 237 and SW CR 18

 