Tentative Work Schedule

July 13, 2022

 

Work in the NW section consists of Grading NW 219th Ter., Mowing ROW on NW 71st. Ave. and Mowing NW CR 125 and NW CR 125 and NW CR 225A

 

Work in the SE section consists of Cleaning out a Concrete Ditch on SE 5th Ave.

 

Work in the SW section consists of Grading SW 101st Ave., Mowing SW CR 235 and SW 161st St. and Patching Pot Holes on SW CR 235 and SW CR 237

 

 

We received 2 DOC (BCSO-JAIL) Officers and No Inmates

 

1 Officer will be assisting in Maintenance 

 

1 Officer will be assisting in Housekeeping