Tentative Work Schedule

September 7, 2023

 

Work in the NW section consists of Grading NW 35th Ave., NW 51st Lane and NW 219th St., Mowing NW CR 229A, NW CR 233 and NW 216th St. and Patching Pot Holes on NW 200th and NW CR 225

 

Work in the SE section consists of Grading SE 129th St., SE 126th St. and SE 134th St. and Patching Pot Holes on SE 52nd 

 

Work in the SW section consists of Grading SW 132nd Ave., SW 130th and SW 127th St.

 

 

We received 2 DOC (BCSO-JAIL) Officers and 3 Inmates and they will be Patching Pot Holes on SE 21st Ave. and on SE 129th St.