Tentative Work Schedule

January 8, 2019

 

Work in the NE section consists of Grading in the NE coming down 301 heading South, Patching pot holes on Carter Road in Lawtey and lightly pulling the ditch on Carter Road

 

Work in the NW section consists of Training on the Road Boss and Grading NW 84th Ave. and NW 185th St., Working on the ditch at NW 84th and 188th, Install culverts on NW 55th Ave. and at NW CR 225 and Patching pot holes on NW 132nd Pl.

 

Work in the SE section consists of Grading SE 58th, SE 31st, SE 50th and along Immokalee Road

 

Work int he SW section consists of Grading SW 105th and SW 163rd and Grading SW 101st and 85th Lane with the Road Boss

 

 

We received 3 DOC Squads for a total of 14 people

 

1 Squad will be Patching pot holes on Carter Road in Lawtey

 

1 Squad will be working at the Shop moving and cleaning areas

 

1 Squad will be directing traffic for Installing culverts on NW 55th Ave. & on NW CR 225