Tentative Work Schedule

November 26, 2019

 

Work in the NW section consists of Grading NW 71st Ave.

 

Work in the SE section consists Building a pad at the Theressa Fire Department

 

Work in the SW section consists of Grading & Shoulder work on SW CR 235, Grading SW 132nd and Mowing SW CR 231 (Dedan Loop) and SW CR 18

 

 

We received 3 DOC Squads for a total of 12 people

 

1 Squad will be Picking up Trash and Weed eating on SW CR 231 (Dedan Loop) and SW CR 18

 

1 squad will be Picking up Trash and Weed eating on SW CR 18 (starting at Brooker end)

 

1 Squad will be directing traffic on SW CR 235