Tentative Work Schedule

June 8, 2021

 

Work NE section consists of Grading Carter Road

 

Work in the NW section consists of Grading NW 200th St. and NW 62nd, Patch driveways on NW CR 229 and Mow ROW on NW 36th Ave. and NW 37th

 

Work in the SE section consists of Grading Crystal Lake Homesites

 

Work in the SW section consists of Mowing SW CR 231 (Dedan Loop) and SW CR 18 and Mowing around Bridges, Signs, Mailboxes, Culverts and Crossover pipes on SW CR 231, SW CR 237 and SW CR 18

 

 

We received 1 DOC Squad (BCSO-JAIL) with 2 Inmates and they will be picking up trash and weed eating on SW CR 231 (Dedan Loop)