Tentative Work Schedule

August 17, 2023

 

Work in the NE section consists of Mowing the Shoulders on NE 179th St.

 

Work in the NW section consists of Grading NW 178th Loop and Mowing the Shoulders on NW 182nd

 

Work in the SE section consists of Paving SE 2nd Ave. and Mowing SE CR 18

 

Work in the SW section consists of Grading SW 163rd St. and Mowing SW CR 225 and SW CR 18

 

 

We received 2 DOC (BCSO-JAIL) Officers and 3 Inmates and they will be handling MOT on SE 2nd Ave. for the Paving crew