Work Schedule

 

Work in the NE section consists of Installing culverts and Patching driveways and pot holes

 

Work in the NW section consists of Pulling ditches & Milling a road, Grading dirt and milled roads and Chipping debris

 

Work in the SE section consists of Installing culverts and Grading milled roads

 

Work in the SW section consists of Grading dirt and milled roads and Installing culverts

 

 

We received3  DOC Squads for a total of 14 people

 

1 Squad will be Chipping debris in the NW

 

1 Squad will be handling traffic control for installation of culverts, emptying trash cans at the Boat Ramps, picking up trash and weed eating

 

1 Squad will be picking up trash and weed eating in the NE & NW

 

 

1 Squad from The Transition House (3 people) will be patching driveways and pot holes