Tentative Work Schedule

August 8, 2023

 

Work in the NE section consists of Cleaning out the Ditch on NE 14th Ave. and Mowing Shoulders in the Petesville area

 

Work in the NW section consists of Grading NW 185th St., NW 188th St. and NW 84th Ave.

 

Work in the SE section consists of Grading SE 41st Ave., SE 46th Ave. and SE 86th St

 

Work in the SW section consists of Grading SW 147th Ave. and SW 120th St., Mowing SW CR 235, SW CR 231 and SW 161st St., Mowing and Cleaning up at the Brooker Community School and Putting up a Speed Sign in Brooker