Tentative Work Schedule

March 15, 2022

 

Work in the NE section consists of Grading NE 6th Ave.

 

Work in the NW section consists of Mowing ROW on NW 180th St. and Patch Driveway and Open up Culvert on NW 71st Ave.

 

Work in the SE section consists of Grading SE 49th Ave.

 

Work in the SW section consists of Grading SW 92nd St. and SW 120th and Installing a Crossover Pipe on SW 66th Ave.

 

 

We received 2 DOC (BCSO-JAIL) Officers and 2 Inmates

 

1 Officer is in Class

 

1 Officer has 2 Inmates and is Picking up Trash and Weed Eating on SW CR 231 (Dedan Loop)