Work in the NE section consists of Grading NE 171st, NE 12th and NE 173rd

 

Work in the NW section consists of Grading roads off of NW CR 125, Opening up ditches on NW 45th Ave. to get water flowing and Mowing Market Road

 

Work in the SE section consists of Mowing the Lincoln City area with the Zero Turn

 

Work in the SW section consists of Repairing SW CR 225A where it was torn up by the Detour from the 301 Traffic Accident on 7/14/2021

 

 

We received 2 DOC (BCSO-JAIL) Squads and 5 Inmates

 

1 Squad will be assisting with the repair of SW CR 225A 

 

1 Squad will be Picking up trash on SE 44th Ave. (Vystar Road)