Tentative Work Schedule

October 1, 2019

 

Work in the NE section consists of Digging the ditch on NE 21st Lane and begin Clearing for new road on NE 20th Lane

 

Work in the NW section consists of Grading NW 41st, Off NW 216th, Olin's Mobile Home Park and Off NW CR 233, Digging the ditch on NW 41st Ave. and NW CR 235 and Patching pot holes on NW 182nd Way (Conerly Estates)

 

Work in the SE section consists of Grading off SE CR 21B, Resetting the base for the Flashing Stop Sign at SE CR 18 & SR 100 and Finish Mowing Keystone Landfill, SE 109th, SE 21st and off of SE CR 100A

 

Work in the SW section consists of Grading SW 101st (Sampson City Cut through) and SW 163rd (Cypress Run Road)

 

 

We did not receive any DOC Squads (they were in lock down)

 

We did receive Bradford County Jail inmates for a total of 4 people.  They will be directing traffic and assist in re-setting Flashing Stop Sign at SE CR 18 & SR 100 then directing traffic for digging the ditch on NE 21st Lane