Tentative Work Schedule

September 18, 2023

 

Work in the NW section consists of Grading NW 203rd, NW 205th and NW 71st, Mowing Shoulders of the Road on NW 177th and NW 180th, Mowing NW CR 225 and Mowing Pratt Street Pond with the Zero Turn

 

Work in the SE section consists of Grading and Fog Sealing SE 11th Ave.

 

Work in the SW section consists of Grading SW 101st and SW 163rd, Moving equipment to SW 106th Ave. and Prepping to Fog Seal and Cleaning out by Culverts on SW 106th Ave.

 

DOC Officer (BCSO-JAIL) will be Cleaning and Weed Eating Ditches and Ditch Paving on SE 5th Ave.