October 21, 2020

 

Work in the NW section consists of Prepping NW 214th St., Repair Culvert on NW 193rd St., Mowing NW 53rd Ave. & NW 219th St., Mulch debris on NW CR 229, Chipping on NW CR 229 and Trimming, cutting limbs and keeping debris off of roadway on NW CR 229 & NW CR 225

 

Work in the SE section consists of Mowing SE CR 18, SE 9th Ave. and SE CR 18A

 

Work in the SW section consists of Chipping on SW CR 227 and SW CR 18 and Grading Crosby Lake area, SW 114th St., SW 180th Ave., SW 180TH Pl. and SW 147th 

 

 

We received 2 DOC Squads for a total of 7 people

 

1 Squad will be assisting with Chipping on SW CR 227, SW CR 18 & NW CR 229

 

1 Squad will be assisting with Chipping on NW CR 229