Work Schedule

 

Work in the NE section consists of Grading and Trimming, Cutting & Chipping

 

Work in the NE section consists of Grading, Digging ditches and Mowing

 

Work in the SE section consists of Zipping a road, Grading and Patching pot holes

 

Work in the SW consists of Digging ditches and Patching and filling in holes and washouts

 

 

We received 3 DOC Squads for a total of 17 people

 

1 Squad will assist in Cutting, Trimming and Chipping in the NE section

 

1 Squad will be picking up trash on SW CR 18

 

1 Squad will be assisting with traffic on NW CR 233 and SW 104th Ave.

 

 

1 Squad from The Transition House  (2 people) will be assisting in patching pot holes in the SE section