Tentative Work Schedule

June 21, 2021

 

Work in the NE section consists of Mowing around Bridges, Guardrails, Mailboxes, Culverts and Crossovers on NE 17th Ave. and NE 14th Ave.

 

Work in the NW section consists of Grading NW 198th and NW 182nd, Mowing ROW NW 198th and NW 124th and  Straightening up the Market Road pit

 

Work in the SE section consists of Grading roads off SE CR 18 going toward Hampton and Mowing the Keystone Landfill

 

Work in the SW section consists of Grading SW 132nd Ave.

 

 

We received 1 DOC (BCSO-JAIL) Squad with 3 Inmates and they will be Trimming the overhanging tree limbs on SW CR 18 sidewalk around Lake Hampton area