Tentative Work Schedule

December 13, 2023

 

Work in the NW section consists of Loading and Hauling Dirt from Market Road Pit to the Landfill and Grading NW 201st St. and NW 74th Ave.

 

Work in the SE section consists of Patching Pot Holes on SE CR 21B

 

 

We received 2 DOC (BCSO-JAIL) Officers and 2 Inmates

 

1 Officer will be with our new Maintenance Director showing him around and Training him

 

1 Officer and 2 Inmates will be Picking up Trash and Weed Eating around Guardrails on SW CR 18 between SW CR 227 and Brooker and on SW CR 225A