Tentative Work Schedule

August 6, 2019

 

Work in the NW section consists of Mowing NW CR 229

 

Work in the SE section consists of Grading SE 46th Loop, SE 36th, SE 87th, SE 16th and Crystal Lake Homesites, Mow Keystone Landfill, Patch Pot Holes on SE 43rd, SE 42nd, SE 41st and SE 2nd and Mow SE Cr 100A, SE 21st Ave & SE 101st with the Half Bat Wing Mower

 

Work in the SW section consists of Grading SW 160th Ave., SW 155th and SW 136th and Mowing SW CR 100A with the Zero Turns and Mowing SW 85th Ln. with the Half Bat Wing Mower

 

 

We received 3 DOC Squads for a total of 15 people

 

1 Squad will be Weed Eating the bridges and guardrails on SW CR 231, SW CR 235 and NW CR 235

 

1 Squad will be Weed Eating the bridges and guardrails on NW CR 225 starting at SW SR 100 and going to 301

 

1 Squad will be Cleaning out the concrete ditches on SE 5th Ave.